The founder and CEO of Ginsburg Architects shares about the details of the plan for renovating the Narkomfin Building (which is about to begin), about the unique system of engineering lines that Moisey Ginsburg proposed for this building, about the necessity of extra survey of the place, and about the project of organizing the building’s adjacent territory that providers for lowering of the driveway level.

Julia Tarabarina

Interviewed by:
Natalya Muradova, Julia Tarabarina
Translated by:
Anton Mizonov

26 June 2017
Interview
mainImg

Archi.ru:
– Why did you decide to go back to the Narkomfin Building renovation project? You did give up on it back in the day, didn’t you?

Aleksey Ginsburg:
– I didn’t exactly give up on it. I stopped working on it because I realized that nothing was happening except conversation. There were outlaw repairs going on, and they kept smuggling authentic elements out of the building. To make things worse, prospects of building annexes that would serve as garages or fitness centers were seriously discussed. Then I made a decision to distance myself as much as possible from that project.

Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


– And when and from what did the new stage of renovation begin? 

– The new stage began in the end of 2015 when the building got a new owner, the company “Liga Prav” (“League of Rights”). It was able to do something that nobody else could do in the last twenty years. It consolidated all the property in the building by simply buying out at an auction the entire building that used to be municipally owned. Mind, these premises are far from attractive – they include corridors and the ground floor that is to be chiefly dismantled. And they also bought out the communal unit, whose top level is also to be dismantled. This company didn’t have any lofty matters or some noble purpose in mind. But if they hadn’t bought it out, no renovation actions would have been possible now.

Once the building got a single owner that has the authority to work with all of its engineering lines and can act as developer and contractor from the legal standpoint, we got the permission to begin our work. I don’t want to name the exact dates because there are other forces at play but the implementation of the project is due to begin in the nearest future. Of course, we will do everything step by step, starting from those parts of the building that are tenant-free.

– And how many people live their currently? Are all the apartments occupied?

– Most of the apartments in that building are rented out, just like they always were. Currently, they have vacated the first two sections for us but, of course, we will work with all the apartments later on.

– What makes the new renovation project different from the old one? 

– This building is really very complex. It has lots of places that I was only able to visit last year, after the building got bought out. And it was only last year that we started doing a survey of these zones. For this survey and design of engineering structures they invited PF “Grado”, while we were invited for the renovation and adaptation in the area of architecture and interior design.

Together we developed the renovation and adaptation project, and the working documents, some parts of it still being issued by us. And we also continue doing some survey. Some minor technological details are still being discussed but generally the project was raised to a whole new level. It’s a lot more elaborate this time.

zooming
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


– In what order will you do the work? Do you have any specific plan for this?

– First, we will do a deconstruction of all these later additions and annexes. I am referring to the communal unit and the first floor. When that is done, we will be able to work with the communal unit in its entirety, and with the north part of the building as well. We want to do our work incrementally. I used to think that this was a wrong thing to do and that a house must be done as a whole. But a deep and detailed survey of the building brought me to a conclusion that it is better to start working with structures and engineering systems in a part of the building in order to field-test many of the methods that we included into the project and the working documents. Because to say that we did the architectural part of the project means to say nothing at all! We explained to the engineers just how the engineering systems in the building were wired because without thinking them out you cannot keep the structure of the building. And we consider keeping the structure of the building intact to be of paramount importance.

– Meaning, keeping the whole engineering structure intact is part of the project? And just what is the condition that these engineering systems are in?

– You cannot just go ahead and renovate the Narkomfin Building. In all the other constructivist buildings you can ultimately settle for as little as keeping the façade intact. But here is the thing – it is the inside structure that makes the Narkomfin Building what it is. It has so many subtleties to it that if you start making changes you will risk ruining it altogether. And our goal is to create a model case – or we will be faced with a prospect of losing the building.

Most of these engineering systems, of course, need to be replaced. For example, the house has inside steel water pipes that are rotten through. But our project provides for solutions that exactly correspond to historical routing. And we insist on that. This historical routing is far from simple. It is at odds with the modern construction rules and regulations.

Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


For example, the sewage in that building was done in this way: there were horizontal sections installed between the third and fourth floors inside the slab casts lying over precast joists.

– Why did they do it like this, anyway?

– There was a water riser that exactly followed the structure of the building. In the spots where the apartments of the “F” type gave way to larger increments of the “K” type it was necessary to switch the horizontal sections – simply because the lower apartments were bigger.

Actually, the inside structure is rather difficult to understand. Some renovators had this straightforward approach: “We’re going to go ahead and just make new risers, and that’s that!” And how exactly are you going to make them? At some places they will run right through the center of the apartment, which, of course, is not an option. You can only run them through the hollow-bodied blocks on the wall or in the same slab casts we spoke about.

Then I had to explain to the engineers that some of the columns of that ground floor were actually quite thick. You can see that in the old photos. Both indoor sanitation and water pipes ran through them. Nobody believed that this could be the case – they would roam around the building looking for the remains of the water pipes. They did everything short of wandering around with water search sticks.

– And what about roof water disposal then? How this was organized? 

– An internal downpipe. It’s a totally modernist narrative. It got clogged up, and nobody cared to unstop it. They made some sort of bypasses which would leak constantly, and the water would ultimately get inside the house. Today’s condition of the building is the logical result of how it was kept all these years.

– But what about the outside walls? They are made of reed pressboard, aren’t they? 

– Alright, let’s speak about the reed pressboard. I had this idea to entertain the people by leaving some fragments of the reed pressboard under glass inside the laundry unit for which we already have the work permit and have the working documents ready – after the renovation it will be turned into a cafe. As a matter of fact, reed pressboard is the precursor of rock wool. This building has many ideas in it that were to become modern construction technologies. And this is what makes it innovative – not just its architecture or organization of space. Reed pressboard served as the thermal insulant or a “heat retainer” between the cip beams of the side walls. Wherever they would come up close to the façade surface, these small spots were filled with it.

– Are these the only places where reed pressboard is to be found? 

– Yes, the only places. The house is built from concrete blocks that were cast directly on the construction site. These blocks were of two types. The first type was “Prokhorov blocks” – they looked very much like the ones that were used in the construction of Bauhaus. They were for the inside walls, and they only had two hollows. And it was these hollows that were used for laying the engineering lines.

"Peasant type" brickwork. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


The other type was called “peasant type”. They were used for the construction of the outside walls. The combination looked as follows: block – setting in broken stone as heat retainer – half-block – stucco – paint. This was the composition of the first three-layer wall. 

– And what are you planning to do with the walls? 

– This is one of the most controversial issues. At some places the walls are ruined, at some places they have been re-laid, and at some places they are in a great condition. Basically, all the damage has to do with water. For example, the east façade is a nightmare to look at. It has hanging flowerbeds upon it, and originally they had openings in them to let the water out. At some point – most likely, after the war – these openings were stopped. There weren’t any cache-pots inside – just soil and plants. So, when it rained, dirty water spilled over and leaked into the cracks between the stucco and the blocks. And if we take the walls of the communal unit or the west façade, they are in a great condition and don’t really need much renovating. But there are the north and south side walls, and these pieces of the east façade that will need to be partially redone.

Blocks designed by the engineer Prokhorov. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


zooming
East facade, preservation chart. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


As for the percentage of losses, we indicated it as a first approximation: only during the process, going from axis to axis and studying each one, we will be able to come up with a more exact figure. Still, though, we will relay the walls with the same blocks. We will make copies of these blocks, and we will recreate the brickwork. There were people who proposed to use breeze blocks or air-bricks but I made and showed them two hand drawings that clearly showed that this would be impossible for purely technical reasons, and not even because of some aesthetic or renovation considerations.

West facade, preservation chart. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


– And why would that be impossible?

– Simply because every material has its size and measurements. Other measurements will change the inside space of the building, and, because it’s pretty compact on the inside, one thing will lead to another. Other materials have a different bulk density that these floors are simply not design to bear.

– Will the façade show in any way, in accordance with the Venice Charter, which part is the authentic one and which is the one that’s been renovated? Or is it still too early to talk about that?

– I like it very much how they renovated Neues Museum in Berlin in accordance with the charter. This is one of my favorite buildings. But when I look at it, what I see is rather a story of a bombed-down museum than a restored one. This memory of destroyed Berlin is an important part of the historical memory of the Germans. 

Do I think that in our case we need to indicate precisely that this square meter is original and this square meter has been renovated? Meaning – do we want our façade look like some kind of skin disease? This is a big question for me.

When I saw the renovated Bauhaus in Dessau, I didn’t notice anything of the kind. All the decoration was executed in a single style, and there was no old-and-new differentiation. On the Izvestia Building I refrained from showing where the old and where the new stained glass windows are. Otherwise the façade would look like some sort of kaleidoscope, and I wanted the building to produce an integral impression. This is a very serious question to me – choosing just which was I should go. I thought about it a lot, and I’m still thinking about it.

Diagram of water affecting the facade. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


– You are saying a lot of things were researched for the first time. Did you discover anything entirely new? 

– Yes, there were things that became a revelation to me. For example, the stained glass window of the communal unit. I always thought that it was dark, the kind that I did on the Izvestia Building. But it turned out to be light-colored, almost white, both on the outside and on the inside. Oh, and, by the way, the building itself wasn’t white, the way they usually portray constructivist architecture. Its original color was different and we are sure to uncover it in the long run. We have already started this research, and we will keep on probing. In addition, we found horizontal “window wells” or “air shafts” that were very fashionable back in the early twentieth century. They are now piled up by some junk, but, of course, we will restore them. 

– And what will happen to the interiors?

– I have a dream. I want to convince the developer to sell apartments in this building as coming with their interior design. If not with the furniture then at least with the ready-made kitchens and bathrooms! It is important for me to show that not a single element in this building appeared by chance, that there was no “design for design’s sake” or “architecture for architecture’s sake”. Every detail mattered, and every detail had a very clear functional meaning. This holds true even for the wall paint.

All the repairs that were done there completely ruined the original decor. We have already taken 49 probes of wall paint from two apartments. Different walls were painted different colors. The “Sovremennaya Arkhitektura” (“Modern Architecture”) magazine published an article by Moisey Ginsburg about how you should go about painting walls; there were two sets of colors there – warm and cold, and then there was this Sheper’s color chart. Now we will analyze these colors and test them against this chart.

West facade, preservation chart. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


Project of recreation the color solutions of the interior designs. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


– Does this mean that the shade of color effectively depended upon the cell type? 

– I don’t know. And nobody will tell you, either. We don’t have any information. We won’t find out anything if we don’t go around with a scalpel and a drill, and our technologist doesn’t research the probes in the laboratory. In the first two apartments that we researched we already ran into the primary and secondary layers of paint. I am very curious myself to find out if all the apartments were painted different colors or the same. Solving this task will be a real treat to me. I am ready to do each apartment individually only to find original colors.

Project of recreation the color solutions of the interior designs © Ginsburg Architects


What else? The developer wants us to make wooden floors. It’s understood that all the xylolite floors were replaced by practically all the tenants with wooden ones, for the exception of, perhaps, Milyutin. He laid carpets on this xylolite. Yes, am OK with making parquet floors but painting the walls original colors is a point of honor to me.

– And what about the Milyutin apartment? Have you already had a chance to get down to his “villa”? 

– Oh, come on, what kind of villa is that? I am ready to share with everyone how the Milyutin apartment came about. It is my firm belief that historical truth must not be lost. Let's start with the humble fact that the Milyutin apartment was not even in the original project. The only reason why it appeared later is because they did not have the money to install a draft ventilation system. But the air handling plant was already there on the roof. And Milyutin decided to make himself an apartment there. They had a quarrel with Ginsburg, and Milyutin said that he would design his apartment himself. He took a cell of Type K, tied it to this volume, and painted it blue. I was there still before they remodeled it and drew the Simpsons on the wall. Now they’ve been painted over but it looked atrocious in any case. We, of course, will recreate the original wall paint. Everything will be done the same way as it is in the other apartments. It’s no different than the other ones. This was basically a funny surreal story: a top statesman got himself a penthouse in the air handling plant next to four rooms of a worker dormitory. Well, he had a right to do as he pleased.

zooming
Left and center: color setting of Cell F. Right: color setting of Cell K / from the Moisey Ginsburg textbook "Zhilishche"


– Before the building changed the owner, one of the last scandals had to do with the fact that millwork was being carried out of the corridors. Was anything left there in the long run?

– A little, but, yes, there was. At least we have something to go on in terms of restoration. We will still try to renovate some small percentage of the windows. Still, we’ve got the drafts, and it’s clear how to do that.

– And what about the kitchen shutters that we read so much about in our textbooks – is there anything left of them?

– I have a growing suspicion that they were never there in the first place. 

– How can this be possible? And what about the draft that we all saw? 

– The drawing that you are referring to is from the “Zhilishche” (“Housing”) textbook, and I love it myself. But I never saw a single photograph of them. Not a single confirmation of their existence! I am not sure they were ultimately installed. When I visited that place as a kid, in spots, where, according to the Ginsburg project, kitchens were supposed to be, there were gas stoves in most of the apartments. In those apartments that I chanced to set my foot in, anyway! Meaning, the place of the “kitchen element” in Cells F was filled with something related to cooking. My dream is to make kitchenettes by the “Zhilishche” sketches, with that corrugated thing; but, of course, we won’t have gas stoves there.

Milyutin's apartment. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


– What else is there in your restoration plans? 

– We want to lower the ground level. Back then, the level of the floor was about 30 centimeters lower than today’s ground level. This is like a restoration program within a restoration program – there have always been a lot of talk how important it was to uncover the first floor. But nobody bothered to analyze just how much must be done in order to uncover it. Meaning, the first challenge that we needed to solve was figure out what to do with the water because the building stands in the lowlands! Currently, water is leaking in from just about everywhere, including the parking lot before “Novinsky Passage”. We did a project for that, did the master plan, got the approvals from Administration for Service to the Diplomatic Corps and the American embassy. Our client got the technical specifications for plugging in to the surface water drain. Only this solution made this whole thing possible. Currently, by the way, we are in the stage of getting an approval from the local police. But, besides all this, there are engineering networks there that we will probably have to sink down even lower. This will also require obtaining technical specifications, extra work, and extra expenses.

zooming
Mini-kitchen in Cell F / from the Moisey Ginsburg textbook "Zhilishche"


Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


– Meaning, the project provides for organization of the territory?

– I want to make a single vehicle-free territory stretching from the American embassy to the park, with an underpass running beneath the building. It’s understood that historically there was earth there, and now it is concrete but I proposed to use the granite paving system that is already accepted in Moscow, just for the sake of uniformity.

– Are there any plans for making a museum in the Narkomfin building?

– We are discussing this question with the client. We are absolutely sure that it’s very important to turn one cell into a museum.
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Structures and elements of the building to be renovated. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Later additions and annexes. Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects
Project of restoration and adaptation of the cultural heritage site "Narkomfin Building" (2015-2017) © Ginsburg Architects


26 June 2017

Julia Tarabarina

Interviewed by:

Natalya Muradova, Julia Tarabarina
Translated by:
Anton Mizonov
Headlines now
New “Flight”
Architects from “Mezonproject” have developed a project for the reconstruction of the regional youth center “Polyot”(“Flight”) in the city of Oryol. The summer youth center, built back in the late 1970s, will now become year-round and acquire many additional functions.
The Yauza Towers
In Moscow, there aren’t that many buildings or projects designed by Nikita Yavein and Studio 44. In this article, we present to you the concept of a large multifunctional complex on the Yauza River, located between two parks, featuring a promenade, a crossroads of two pedestrian streets, a highly developed public space, and an original architectural solution. This solution combines a sophisticated, asymmetric façade grid, reminiscent of a game of fifteen puzzle, and bold protrusions of the upper parts of the buildings, completely masking the technical floors and sculpting the complex’s silhouette.
Architecture and Leisure Park
For the suburban hotel complex, which envisages various formats of leisure, the architectural company T+T Architects proposed several types of accommodation, ranging from the classic “standard” in a common building to a “cave in the hill” and a “house in a tree”. An additional challenge consisted in integrating a few classic-style residences already existing on this territory into the “architectural forest park”.
The U-House
The Jois complex combines height with terraces, bringing the most expensive apartments from penthouses down to the bottom floors. The powerful iconic image of the U-shaped building is the result of the creative search for a new standard of living in high-rise buildings by the architects of “Genpro”.
Black and White
In this article, we specifically discuss the interiors of the ATOM Pavilion at VDNKh. Interior design is a crucial component of the overall concept in this case, and precision and meticulous execution were highly important for the architects. Julia Tryaskina, head of UNK interiors, shares some of the developments.
The “Snake” Mountain
The competition project for the seaside resort complex “Serpentine” combines several typologies: apartments of different classes, villas, and hotel rooms. For each of these typologies, the KPLN architects employ one of the images that are drawn from the natural environment – a serpentine road, a mountain stream, and rolling waves.
Opal from Anna Mons’ Ring
The project of a small business center located near Tupolev Plaza and Radio Street proclaims the necessity of modern architecture in a specific area of Moscow commonly known as “Nemetskaya Sloboda” or “German settlement”. It substantiates its thesis with the thoroughness of details, a multitude of proposed and rejected form variants, and even a detailed description of the surrounding area. The project is interesting indeed, and it is even more interesting to see what will come of it.
Feed ’Em All
A “House of Russian Cuisine” was designed and built by KROST Group at VDNKh for the “Rossiya” exhibition in record-breaking time. The pavilion is masterfully constructed in terms of the standards of modern public catering industry multiplied by the bustling cultural program of the exhibition, and it interprets the stylistically diverse character of VDNKh just as successfully. At the same time, much of its interior design can be traced back to the prototypes of the 1960s – so much so that even scenes from iconic Soviet movies of those years persistently come to mind.
The Ensemble at the Mosque
OSA prepared a master plan for a district in the southern part of Derbent. The main task of the master plan is to initiate the formation of a modern comfortable environment in this city. The organization of residential areas is subordinated to the city’s spiritual center: depending on the location relative to the cathedral mosque, the houses are distinguished by façade and plastique solutions. The program also includes a “hospitality center”, administrative buildings, an educational cluster, and even an air bridge.
Pargolovo Protestantism
A Protestant church is being built in St. Petersburg by the project of SLOI architects. One of the main features of the building is a wooden roof with 25-meter spans, which, among other things, forms the interior of the prayer hall. Also, there are other interesting details – we are telling you more about them.
The Shape of the Inconceivable
The ATOM Pavilion at VDNKh brings to mind a famous maxim of all architects and critics: “You’ve come up with it? Now build it!” You rarely see such a selfless immersion in implementation of the project, and the formidable structural and engineering tasks set by UNK architects to themselves are presented here as an integral and important part of the architectural idea. The challenge matches the obliging status of the place – after all, it is an “exhibition of achievements”, and the pavilion is dedicated to the nuclear energy industry. Let’s take a closer look: from the outside, from the inside, and from the underside too.
​Rays of the Desert
A school for 1750 students is going to be built in Dubai, designed by IND Architects. The architects took into account the local specifics, and proposed a radial layout and spaces, in which the children will be comfortable throughout the day.
The Dairy Theme
The concept of an office of a cheese-making company, designed for the enclosed area of a dairy factory, at least partially refers to industrial architecture. Perhaps that is why this concept is very simple, which seems the appropriate thing to do here. The building is enlivened by literally a couple of “master strokes”: the turning of the corner accentuates the entrance, and the shade of glass responds to the theme of “milk rivers” from Russian fairy tales.
The Road to the Temple
Under a grant from the Small Towns Competition, the main street and temple area of the village of Nikolo-Berezovka near Neftekamsk has been improved. A consortium of APRELarchitects and Novaya Zemlya is turning the village into an open-air museum and integrating ruined buildings into public life.
​Towers Leaning Towards the Sun
The three towers of the residential complex “Novodanilovskaya 8” are new and the tallest neighbors of the Danilovsky Manufactory, “Fort”, and “Plaza”, complementing a whole cluster of modern buildings designed by renowned masters. At the same time, the towers are unique for this setting – they are residential, they are the tallest ones here, and they are located on a challenging site. In this article, we explore how architects Andrey Romanov and Ekaterina Kuznetsova tackled this far-from-trivial task.
In the spirit of ROSTA posters
The new Rostselmash tractor factory, conceptualized by ASADOV Architects, is currently being completed in Rostov-on-Don. References to the Soviet architecture of the 1920’s and 1960’s resonate with the mission and strategic importance of the enterprise, and are also in line with the client’s wish: to pay homage to Rostov’s constructivism.
The Northern Thebaid
The central part of Ferapontovo village, adjacent to the famous monastery with frescoes by Dionisy, has been improved according to the project by APRELarchitects. Now the place offers basic services for tourists, as well as a place for the villagers’ leisure.
Brilliant Production
The architects from London-based MOST Architecture have designed the space for the high-tech production of Charge Cars, a high-performance production facility for high-speed electric cars that are assembled in the shell of legendary Ford Mustangs. The founders of both the company and the car assembly startup are Russians who were educated in their home country.
Three-Part Task: St. Petersburg’s Mytny Dvor
The so-called “Mytny Dvor” area lying just behind Moscow Railway Station – the market rows with a complex history – will be transformed into a premium residential complex by Studio 44. The project consists of three parts: the restoration of historical buildings, the reconstruction of the lost part of the historical contour, and new houses. All of them are harmonized with each other and with the city; axes and “beams of light” were found, cozy corners and scenic viewpoints were carefully thought out. We had a chat with the authors of the historical buildings’ restoration project, and we are telling you about all the different tasks that have been solved here.
The Color of the City, or Reflections on the Slope of an Urban Settlement
In 2022, Ostozhenka Architects won a competition, and in 2023, they developed and received all the necessary approvals for a master plan for the development of Chernigovskaya Street for the developer GloraX. The project takes into account a 10-year history of previous developments; it was done in collaboration with architects from Nizhny Novgorod, and it continues to evolve now. We carefully examined it, talked to everyone, and learned a lot of interesting things.
A Single-Industry Town
Kola MMC and Nornickel are building a residential neighborhood in Monchegorsk for their future employees. It is based on a project by an international team that won the 2021 competition. The project offers a number of solutions meant to combat the main “demons” of any northern city: wind, grayness and boredom.
A New Age Portico
At the beginning of the year, Novosibirsk Tolmachevo Airport opened Terminal C. The large-scale and transparent entrance hall with luminous columns inside successfully combines laconism with a bright and photogenic WOW-effect. The terminal is both the new façade of the whole complex and the starting point of the planned reconstruction, upon completion of which Tolmachevo will become the largest regional airport in Russia. In this article, we are examining the building in the context of modernist prototypes of both Novosibirsk and Leningrad: like puzzle pieces, they come together to form their individual history, not devoid of curious nuances and details.
A New Starting Point
We’ve been wanting to examine the RuArts Foundation space, designed by ATRIUM for quite a long time, and we finally got round to it. This building looks appropriate and impressive; it amazingly combines tradition – represented in our case by galleries – and innovation. In this article, we delve into details and study the building’s historical background as well.
Molding Perspectives
Stepan Liphart introduces “schematic Art Deco” on the outskirts of Kazan – his houses are executed in green color, with a glassy “iced” finish on the facades. The main merits of the project lie in his meticulous arrangement of viewing angles – the architect is striving to create in a challenging environment the embryo of a city not only in terms of pedestrian accessibility but also in a sculptural sense. He works with silhouettes, proposing intriguing triangular terraces. The entire project is structured like a crystal, following two grids, orthogonal and diagonal. In this article, we are examining what worked, and what eventually didn’t.
An Educational Experiment for the North
City-Arch continues to work on the projects that can be termed as “experimental public preschools”: private kindergartens and schools can envy such facilities in many respects. This time around, the project is done for the city of Gubkinsky, Yamalo-Nenets Autonomous District. A diverse educational and play environment, including a winter garden, awaits future students, while the teachers will have abundant opportunities to implement new practices.
Alexandra Kuzmina: “Working is easy when the rules are the same for everyone”
The subject matter of Moscow Region’s booth and presentations at Zodchestvo Festival was the concept of “Integrated Land Development”, and for a good reason: this task is very challenging, very relevant, and Moscow Region has already accumulated quite a formidable experience in this regard. In this article, we are speaking to the main architect of the region: about master plans and who makes them, about where you obtain resources for creating a comfortable environment, about her favorite projects, about why there are so few good architects, and what we should do with the bad ones.
The Cemetery: Inside and Outside
The workshop organized by the Genplan Institute of Moscow scored one of the two first places at the “Open City” festival. Its subject is reorganization of municipal cemeteries. Two action plans were proposed, diametrically opposite: one for the downtown and one for the suburbs.
Our Everything
Who is Alexey Shchusev? In the last couple of weeks, since the architect’s 150th birthday, different individuals have answered this question differently. The most detailed, illustrated, and elegantly presented response is an exhibition held in two buildings of the Museum of Architecture on Vozdvizhenka. Four curators, a year and a half of work performed by the entire museum, and exhibition design by Sergey Tchoban and Alexandra Sheiner – in this article, we take you on a tour of the exhibition and show what’s what in it.
For Mental Reboot
At the architectural competition held in 2023 in Novosibirsk, the project by GORA Architects – a pedestrian bridge leading to the town of Bor – was awarded the “Golden Capital” prize. In this country, more than a hundred pedestrian bridges are constructed each year. What makes the Bor bridge different?
Gold Embroidery
A five-story housing complex designed by Stepan Liphart in Kazan, responds to the stylistically diverse context with its form, both integral and agile, and as for the vicinity of the “Ekiyat” movie theater, the complex responds to it with a semblance of theater curtain folds, and active plastique of its balconies, that bear some resemblance to theater boxes. Even if excessively pompous a little bit, the complex does look fresh and modern. One will have a hard time finding Art Deco elements in it, even though the spirit of the 1930s, run through the filter of neo-modernism, is still clearly felt, just as a twist of the Occident.